These are the artifacts I build and run on real programs, rebuilt as sanitized samples. The structures are mine; project names and details are illustrative, and the adoption figures are the public OPNAV-GPT numbers.

Portfolio management

Portfolio health board

Projects roll up to programs and programs to the portfolio. Leadership reads one line per initiative: health, phase, the next decision needed, and open dependencies.

Illustrative sample
InitiativeProgramPhaseHealthNext decisionDeps
Secure AI assistant rolloutEnterprise AILight the pathOn trackApprove SIPR onboarding wave 34
Repository migration to SharePoint OnlinePlatform modernizationDraw the linesWatchConfirm retention labels with records officer6
Service desk modernization (JSM)Service operationsHold the orbitOn trackAccept SLA dashboard2
Knowledge base restructureKnowledge managementMap the skyAt riskName a content owner per space3
Event platform requirementsProgram operationsDraw the linesOn trackSign off on the requirements baseline1

Adoption metrics

Adoption dashboard: OPNAV-GPT

Adoption tracked like delivery: by network, by wave, and by what users can reach. Public figures, rounded down.

Public figures
Pilot
250+
NIPR users
3,500+
SIPR users
3,700+
Total users
7,200+
3,900+knowledge assets available to OPNAV-GPT users
55+enterprise data sources supporting secure AI use
50+reusable prompts in the OPNAV-GPT library
10+cross-functional workstreams coordinated as delivery lead

Prioritization

WSJF scoring

Weighted Shortest Job First: cost of delay (business value + time criticality + risk reduction) divided by job size. The highest score goes first, and the math ends most priority debates.

Illustrative sample
FeatureBusiness valueTime criticalityRisk reductionCost of delayJob sizeWSJF
Single sign-on for secure-network users131383456.8
Prompt library, version 28531635.3
Records retention labels58132683.3
Usage analytics dashboard8351653.2

Governance

RAID log

Risks, assumptions, issues, and dependencies, each with an owner, a response, and a status reviewed weekly.

Illustrative sample
IDTypeDescriptionOwnerResponseStatus
R-01RiskAccount provisioning on the secure network takes longer than the onboarding windowPlatform leadPre-stage accounts one wave ahead; track in JiraAt risk
A-02AssumptionContent owners will review migrated libraries within two weeksDelivery leadConfirm in writing at kickoff; escalate at day 10Watch
I-03IssueTraining sessions conflict with a command exerciseAdoption leadRecord sessions; add office hours the following weekOn track
D-04DependencySecurity accreditation update before the next releaseCyber teamWeekly sync; release gate in JiraWatch

Ownership

RACI matrix

One accountable owner per activity. Most stalled decisions trace back to two.

ActivitySponsorDelivery leadPlatform teamData ownersAdoption lead
Prioritize the backlogARCCC
Configure workflows and permissionsIARCI
Approve data sourcesICCA/RI
Training and communicationsIACIR
Release go / no-goARCCC

R responsible · A accountable · C consulted · I informed

Risk

Risk heat map

Likelihood × impact. Anything in the top-right gets an owner and a dated response this week.

Likelihood 15

Vertical axis: impact 1 to 5. R1 provisioning delays · R2 accreditation timing · R3 content owner availability · R4 training conflicts.

Jira

JQL behind leadership dashboards

Leadership reporting should come straight from the board, not a separate spreadsheet. These filters power the gadgets I build for sponsors and program leads.

Working JQL

Overdue work leadership should see

project in (DLV, PLAT) AND statusCategory != Done
  AND duedate < now() ORDER BY priority DESC, duedate ASC

Blocked items and who they wait on

project = DLV AND (status = Blocked OR "Flagged" is not EMPTY)
  ORDER BY updated ASC

Adoption stories in the current increment

project = DLV AND labels = adoption
  AND sprint in openSprints() ORDER BY rank

Aging service requests past SLA

project = HELP AND "Time to resolution" = breached()
  AND resolution = Unresolved ORDER BY created ASC

Executive reporting

One-page status pack

Decisions first, then risks, then progress. A sponsor should know what is needed from them in the first ten seconds.

Illustrative sample

Decisions needed this week

  • Approve onboarding wave 3 for secure-network users (sponsor)
  • Name a content owner for each knowledge space (division leads)

Top risks

  • Account provisioning lead time exceeds the onboarding window. Response: pre-stage one wave ahead.

Progress

Wave 2 complete. Training attendance at target. Prompt library expanded; usage analytics dashboard in build.

Next two weeks

Wave 3 onboarding, retention label sign-off, and the 30-day adoption check for wave 2.

Live proof of concept

How this site runs

This website is wired into the same stack I run for programs. Every inquiry becomes a Jira ticket and a SharePoint record, and Field Notes are written and reviewed in Confluence before they publish here.

Working system

1 · Intake

Website forms

Questionnaire, downloads, and Field Notes submissions post to a secure serverless function on Cloudflare.

2 · Triage

Jira Service Management

Each submission opens a ticket in a dedicated queue, labeled by type, with SLAs and automation for follow-up.

3 · Record

SharePoint Online

Power Automate writes the same submission to a SharePoint list: the relationship register and reporting source.

4 · Publish

Confluence

Field Notes and templates are drafted and approved in Confluence, then synced to this site at build time.

The site’s own roadmap is a Jira board, and its runbook lives in Confluence. Same governance, smaller scale.

Work with me

Discuss a role or engagement

A short questionnaire helps me prepare for our first conversation. It takes about three minutes.

Stay in touch through Field Notes

Monthly lessons from real federal delivery work, plus new templates and prompts as they’re released.

One email a month. Unsubscribe anytime. Privacy

You’re on the list. Thank you. Your email app opened with a short message. Press send to confirm.